Orient Substation

Orient Substation

Location: Orient, IA
Description: Construction of a substation including 429 piers ranging in diameter from 36-inch to 66-inch and depths of up to 36-feet deep. CMG furnished and constructed all drilled pier foundations, 3 transformer pads and containments, and over 7000 lineal feet of electrical duct bank.
Owner: MidAmerica Energy
Contractor: EPC Services


 