Rich to Swartwout 138kV Transmission Line

Rich to Swartwout 138kV Transmission Line

Location: Livingston, TX

Description: 43 total drilled shafts (35 direct bury and 9 anchor bolt) drilled using the slurry method for a new transmission line. The scope of work included drilling direct bury foundations and drilling, setting anchor bolt cages, and pouring anchor bolt foundations. Drilled shaft diameters ranged from 48” to 90” and were drilled up to 25’ deep.

Owner: East Texas Electric Cooperative
Contractor: North Houston Pole Line

 


 